Odisha has received approval for its
second semiconductor unit
¨
Odisha has received
approval for its second semiconductor unit on 15 September 2026.
¨
The project is a silicon
carbide semiconductor device manufacturing facility to be established by M/s
SiCSem Private Limited.
¨
The project involves an
investment of ₹3,406.25 crore.
¨
The facility will be
established at IDCO Infovalley-II in Arisol Mouza, under Jatni tehsil of
Khordha district, Odisha.
¨
The project is located
within the Falta Special Economic Zone.
¨
Silicon carbide (SiC) is
a wide-bandgap semiconductor material suitable for high-power and
high-temperature applications.
¨
SiC devices are used in
electric vehicles, renewable energy systems, railways, and defence electronics.
¨
SiC devices can operate
at higher voltages and temperatures than many conventional silicon-based
semiconductor devices.
¨
The facility will
manufacture SiC diodes and SiC MOSFETs.
¨
The proposed annual
production capacity is 4.8 million SiC diodes.
¨
The proposed annual
production capacity is 91.2 million SiC MOSFETs.
¨
The project will cover an
area of 21.889 acres.
¨
The project received
approval at the 217th meeting of the Unit Approval Committee held on 29 August
2026.
¨
The facility is expected
to create approximately 1,270 direct employment opportunities.
¨
The proposed funding
includes ₹700 crore central capital subsidy.
¨ The Odisha government will provide a ₹350 crore subsidy.
¨ The remaining ₹1,956.25 crore will come through promoter contribution.